Friday 22 March 2013

Progress at SEB






It's taken us 6 weeks to achieve but I think it will be worth the effort. The paddling pool in the middle is a specialist resin floor, falling gently to a stainless steel drain in the centre; this is where our conditioning tanks will sit, all snug & squeaky clean. The walls are covered in an anti-bactericidal coating to discourage potential contaminants.

Through those doors is the filling room: empties enter left; fullies exit right. The area is similarly appointed with resin flooring, stainless drains & anti-bac' wall coating.


 Next up: compressed air, carbon dioxide, electricity & water services.


1 comment:

Steve said...

Looks great. What location is it in?